At 5:12 a.m. on December 14, 2005, the northwest side of the upper reservoir was overtopped when water continued to be pumped from the lower reservoir after the upper was full. This led to the catastrophic failure of a triangular section of the reservoir wall and the release of 1 billion US gallons (3.8 Gl) of water in twelve minutes. The sudden release sent a 20-foot (6.1 m) crest of water down the East Fork of the Black River.